Commencement certificate: who issues it and what happens if you skip it

Table of contents

  • What is a commencement certificate?
  • Where it fits in the approval sequence
  • Who issues it in each city?
  • How to apply
  • What happens if you start without approval?
  • The Last Word
  • FAQs
  • References

Key takeaways

  • A commencement certificate is not one national document: its name, timing and format depend on the local authority.
  • A sanctioned building plan approves the drawings, while commencement notices and stage inspections govern when work can start or continue.
  • In Bengaluru, Section 239 of the Greater Bengaluru Governance Act, 2024, provides for a plinth certificate once construction reaches plinth level.
  • In Hyderabad, Section 440 of the GHMC Act requires notice to the City Engineer of the proposed commencement date.
  • Starting without a required permission or notice can lead to stop-work action, penalties and problems at the occupancy and resale stages.

A sanctioned building plan does not always mean work can start. In many places, the commencement certificate, or an equivalent notice or inspection, is the go-ahead to begin digging or to build beyond plinth level. This guide explains what a commencement certificate is, where it fits in the approval sequence, who issues it in each city, how to apply and what happens if construction starts without it.

What is a commencement certificate?

A commencement certificate (CC) is a term used in some local building approval processes to indicate that construction is authorised to begin or proceed beyond a specified stage.

It is important to distinguish a commencement certificate from building plan approval. A sanctioned plan confirms that the proposed drawings have been approved under the applicable rules. A commencement notice or certificate relates to the start of construction or a particular stage of work.

The terminology and process differ between cities. Some authorities require a separate commencement notice. Others require an inspection and certificate after construction reaches plinth level. In certain cases, the relevant permission and commencement conditions form part of the building approval itself.

A commencement-related document does not establish clear land title. Ownership and title checks are separate parts of the property due diligence process.

A commencement certificate or notice is usually valid only for a set period, often linked to the building permission. If work does not start, or does not reach the next stage, within that period, the owner may need to renew the permission or give a fresh notice. The permission order states the applicable dates.

Where it fits in the approval sequence

The construction approval process generally follows this sequence:

  • Land and title checks: Verify ownership, land use and relevant property records.
  • Building plan approval: Obtain the required building permission and sanctioned plan.
  • Commencement requirements: Complete the applicable commencement notice, certificate or registration process.
  • Construction and inspections: Arrange inspections at the stages required by the local authority.
  • Completion documentation: Submit the required completion documents and certificates.
  • Occupancy approval: Obtain an occupancy certificate where the applicable rules require one.

The exact sequence depends on the local building rules. For example, a plinth-level inspection is not the same as a separate certificate to begin excavation.

Who issues it in each city?

The authority and process depend on the property's location. The table below shows who handles commencement-stage approvals in four locations.

CityIssuing bodyOnline portalNotes
BengaluruThe relevant city corporation under the Greater Bengaluru AuthorityNAPlinth certificate at plinth level: Section 239, Greater Bengaluru Governance Act, 2024
HyderabadGHMC, Cyberabad or Malkajgiri Municipal Corporation, depending on locationBuildNowNotice of commencement to the City Engineer: Section 440, GHMC Act, 1955
ChennaiCMDA (planning permission) and the local body, such as the Greater Chennai Corporation (building permit)Tamil Nadu Single Window PortalNotice before work starts (Rule 9) and continuance order at plinth level (Rule 20): TNCDBR 2019
KeralaMunicipality, corporation or Grama PanchayatLSGD building permit portalKerala Municipality or Panchayat Building Rules, 2019, both amended 29 October 2025

Bengaluru

Search results still refer to a commencement certificate from BBMP, but Bengaluru's civic functions have moved to the Greater Bengaluru Authority and its city corporations. The Greater Bengaluru Governance Act, 2024 (Karnataka Act No. 36 of 2025), now sets the framework for building permission in the city.

Section 239 of the Act provides for a plinth certificate once the building reaches plinth level. This is a stage certificate, distinct from the building permission and sanctioned plan, and should not be confused with a general commencement certificate issued before excavation. Check the current procedure with the relevant city corporation before work starts.

Hyderabad

Section 440 of the Greater Hyderabad Municipal Corporation Act, 1955, sets out when building work may commence.

The owner must first follow the applicable building-permission process. The owner must also notify the City Engineer of the proposed commencement date. If work does not begin within seven clear days of the date notified, the notice is treated as not having been given.

The one-year period referred to in Section 440 relates to the period for proceeding with work under Sections 437 and 438. It is not a general one-year validity period for a separate commencement certificate.

Since 11 February 2026, the former GHMC area has been split between the Greater Hyderabad, Cyberabad and Malkajgiri Municipal Corporations (G.O.Ms.No.55), and building applications in all three go through the BuildNow portal. Check the corporation that covers the plot, and the GHMC Act, before starting work.

Chennai

In Chennai, two approvals usually apply. Under Rule 5 of the Tamil Nadu Combined Development and Building Rules, 2019, planning permission in the Chennai Metropolitan Area is issued by the Chennai Metropolitan Development Authority (CMDA), or by a local body to which CMDA has delegated the power. The local body's executive authority issues the building permit, such as the Greater Chennai Corporation.

Rather than a separate commencement certificate, the rules set out two steps. Rule 9 requires the owner to notify the authority, in the prescribed form, before starting work at the site. Once the building reaches plinth level, the owner applies for a continuance order. Under Rule 20, if the order is not issued within 15 days of the application, it is deemed to be issued.

The CMDA progress certificate and completion certificate inspection procedure explains the plinth-level inspection, which confirms the commencement of work at the site. For a wider view of permissions in the city, see the guide to home construction approvals in Chennai.

Kerala

Kerala has separate building rules for municipal areas and panchayat areas. The local body responsible for the property determines which rules apply.

The Kerala Municipality Building Rules, 2019, and Kerala Panchayat Building Rules, 2019, have both been amended. The relevant amendments were notified on 29 October 2025 as S.R.O. 1240/2025 and S.R.O. 1241/2025 respectively.

Owners should check the applicable permit, commencement and inspection requirements with their municipality, corporation or Grama Panchayat. Do not rely on the original 2019 rules without checking the amendments.

The Kerala LSGD Gazette notifications provide access to the official amendments.

How to apply

The documents needed for a commencement certificate for building work vary by local authority. These steps provide a general checklist, not a substitute for the requirements in your building-permission order.

  • Confirm the applicable rules. Identify the local authority and check whether your property requires building permission, a commencement notice, a separate certificate or a stage inspection.
  • Obtain the sanctioned plan. Keep the approved building plan and permission order available.
  • Prepare the required documents. Depending on the local process, these may include ownership records, khata or equivalent property records, structural drawings, fee receipts and applicable No Objection Certificates.
  • Submit the required application or notice. Use the official building-permission portal or the procedure specified by the local authority.
  • Arrange inspections. If the rules require a site inspection at commencement or plinth level, apply at the prescribed stage.
  • Keep the records. Retain the permission order, submitted notices, inspection reports and certificates for future reference.

What happens if you start without approval?

Starting construction without a required building permission, notice or certificate creates a compliance risk. The consequences depend on the applicable law and the nature of the violation.

Stop-work action and enforcement

The local authority may issue a notice directing the owner to stop work if construction violates the applicable permission or building rules. Serious or unauthorised deviations may lead to further enforcement, including penalties or demolition orders where the law permits.

Problems with completion and occupancy approval

If the construction record is incomplete, or the building does not match the sanctioned plan, the owner may face difficulties during completion or occupancy approval. The authority may require additional documents, inspections or corrective work.

A missing commencement-related document does not automatically mean that an occupancy certificate will be refused in every jurisdiction. The outcome depends on the local rules and the facts of the case.

Resale complications

During resale, buyers may ask for the sanctioned plan, building permissions and completion or occupancy documents. Gaps in the approval record can delay due diligence and the transaction.

The Last Word

Before the first excavation, check which document the local authority requires: a commencement certificate, a commencement notice or a plinth certificate. Starting with the right certificate in hand keeps the later approvals, including completion and occupancy, simpler. Keep every notice and inspection record, and build to the sanctioned plan. Plan your build with JSW One Homes once approvals are in place.

FAQs

What is the meaning of a commencement certificate?

A commencement certificate is a document issued by a local authority that allows construction to begin, or to continue past a set stage such as plinth level. In property paperwork, the short form CC can also mean a completion certificate, which comes at the end of construction. When a buyer or official asks for the CC, check which of the two documents they mean, since one marks the start of work and the other marks its end.

Is a commencement certificate needed for an independent house?

It depends on the location, plot size and building category. Some local rules exempt small residential buildings from parts of the permission process or offer a simplified registration route, while others require notice before work starts or an inspection at plinth level. Even where no separate certificate exists, the building permission usually carries conditions on when and how work may begin. Read the permission order closely and confirm the requirement with the local body before excavation starts.

How long is a commencement certificate valid?

There is no single national validity period. The local building rules and the permission order set the relevant dates, and many authorities tie validity to the building permission rather than to a separate commencement document. If work is delayed, check whether the permission needs renewal before it lapses. Starting or continuing work on an expired permission carries the same risks as starting without one, so note the expiry date as soon as the order is issued.

What is a BBMP commencement certificate now called?

Bengaluru's civic administration has moved from the BBMP to the Greater Bengaluru Authority and its city corporations under the Greater Bengaluru Governance Act, 2024. Searches for a BBMP commencement certificate usually refer to the permission stage around the start of construction. Under the current Act, Section 239 provides for a plinth certificate once the building reaches plinth level. Check the current requirements with the relevant city corporation rather than relying on older BBMP guidance.

Who issues commencement approvals in Hyderabad now?

Since February 2026, three corporations cover the former GHMC area: the Greater Hyderabad, Cyberabad and Malkajgiri Municipal Corporations, constituted under G.O.Ms.No.55 of 11 February 2026. Building applications in all three go through the BuildNow portal, which replaced TG-bPASS after 15 December 2025. The plot's property tax records usually show which corporation covers it. Confirm the commencement-notice requirement with that corporation before work starts.

Does JSW One Homes apply for the commencement certificate?

No. The JSW One Homes FAQ states that "customers are required to obtain government approvals independently", and regulatory approvals are listed among the exclusions from the design package. Owners therefore apply for the building permission, any commencement notice or certificate and any stage inspections themselves, through the local authority's process. Keep copies of these approvals ready when planning the build.